Finalist #6 Mah Sing Foundation

Mega Scale Gravity Water Project 2019

GOAL 6: CLEAN WATER AND SANITATION

The project started on June 30, 2019, with the building and repairing of the concrete water catchment and replacing the villages’ PVC pipes to polypipe at Kadamaian area in Kota Belud.
The upgrading and building work took about four to five months to complete with the total length of piping at 11km. With the completion of the project, we managed to improve the livelihood of more than 3,400 rural villagers by providing them with a safe and sustainable water supply. The access to the water supply also reduced the average travelling to-and-fro the water source, which then provides them more time for the community to focus their
efforts in earning a living and taking care of their families.